2024
Disassembly - transport - new assembly of a 20/400KV - 360MW Transformer and overhead energy lines 400kKV

ELPEDISON

2023
Restoration of Substation at Volos

TERNA SA

2023
Complete erection of electromechanical works for AdG Substation

MYTILINEOS

2022
Erection of two HV (400 kV) gates at Distomon High Voltage Plant

MYTILINEOS GROUP / METKA

2019
Installation of LV system for operation at substations Anthili and Perivoli of OSE

SIEMENS HELLAS S.A.

2014
Revampig of two (2) substations at Sfiga and Acharnes

ALSTOM Transport S.A.

2013
Complete erection of electrical equipment at a 150 kV Switchyard and, MV Switchgear at Ilarion H.E.P. And at Ilarion Small H.E.P.

METKA

1997
Construction of one 200kV G.I.S. Substation at S.E.S. Lavrio

SIEMENS (P.P.C.)